Chapter 3. Project Planning

23

Draft Document for Review May 23, 2008 10:14 am

7645ProjPlan.fm

Key Activities:

Identify module requirements

Identify configuration requirements in terms of:

– Roles
– Security groups
– Escalations
– Communication Templates
– Work Order Templates
– Job plans
– SLAs
– Vendors and Contracts
– Screen configurations
– GL Codes

Create a detailed implementation plan

Identify methodology for integration

Identify scripting or manual data migration approach from identified data
sources

Create a solution architecture diagram

Phase 3: Deployment

Roles Involved: Project Manager, Solution Architect, Maximo Developers

Optional Roles: DBA, Application Server Specialist (depending on environment)

Key Activities:

This phase consists of the following activities:

Software Installation

– Install the various components if doing a Manual install
– Run the launchapd for an automated install
– Test if the installation is successful

The software installation will be different for various deployment topologies -
single server, multi-server, clustered environment. It will also depend on what
infrastructure is selected.

Software Configuration

– Basic operation configuration which includes, but is not limited to:

Creation of organization

Creation of locations

Creation of GL Codes

Advertising