Site preparation checklist – Juniper Networks M5 User Manual

Page 72

Advertising
background image

Site Preparation Checklist

the power to bring it within the allowable range; for short lengths of fiber, with fiber and
connector loss close to zero, an attenuator of 5 to 10 dB should be sufficient.

For specifications of minimum and maximum input level (receiver sensitivity and receiver
saturation) and minimum and maximum output level (average launch power) for the
SONET/SDH PICs supported on the M5 and M10 routers, see the M5 and M10 Internet
Routers PIC Guide
.

Cable Specifications for Routing Engine Management Interfaces

For management and service operations, you connect the Routing Engine to an external
console or management network through ports on the craft interface. For information about
the ports, see “Routing Engine Interface Ports and Status Indicators” on page 15.

Table 13 lists the specifications for the cables that connect to management ports.

Table 13: Cable Specifications for Routing Engine Management Interfaces

Port

Cable
Specification

Cable/Wire
Supplied

Maximum
Length

Router
Receptacle

Routing Engine
console or
auxiliary
interface

RS-232 (EIA-232)
serial

One 6-ft (1.83-m)
length with
DB-9/DB-9
connectors

6 ft (1.83 m)

DB-9 male

Routing Engine
Ethernet
interface

Category 5 cable
or equivalent
suitable for
100BaseT
operation

One 15-ft (4.57-m)
length with
RJ-45/RJ-45
connectors

328 ft (100 m)

RJ-45
autosensing

Site Preparation Checklist

The checklist in Table 14 summarizes the tasks you need to perform when preparing a site
for router installation.

Table 14: Site Preparation Checklist

Item or Task

Performed
By

Date

Notes

Verify that environmental factors such
as temperature and humidity do not
exceed router tolerances (see “Router
Environmental Tolerances” on page 40).

Measure distance between external power
sources and router installation site.

52

M5 and M10 Internet Routers Hardware Guide