Small Power Substation Transformers

Document 2.4.54 Revision 0

July 2006

9

Installation of Surge Arresters

Surge arresters should be installed according to the

following instructions and the outline drawing.

!

WARNING: FAILURE TO FOLLOW THESE

INSTRUCTIONS COULD RESULT IN SEVERE

PERSONAL INJURY, DEATH, OR EQUIPMENT

DAMAGE.

1. Carefully unpack and inspect surge arresters

for damage.

2. When installing arresters, all mounting feet

must be flush with the mounting surface before

tightening bolts. Use shims if necessary.

3. Do not climb or stand on arrester. Do not place

undue mechanical stress on arrester.

4. Use only the lifting devices provided on the

arrester for lifting.

5. Arrester exhaust ports (if supplied) must be

oriented so that exhaust will be directed away

from other arresters and other equipment.

Installation of Air Terminal Chamber and

15 KV and 5 KV Switchgear Adapters

Air terminal chambers are designed to protect

personnel from high voltages and to provide a clean,

dry environment for bushings. Air terminal chambers

must be installed according to instructions on the

drawing. Refer to transformer outline drawing, detail

drawing, and station plan drawing.

!

WARNING: IMPROPER INSTALLATION OF

CONNECTING CHAMBERS AND ADAPTERS

MAY ALLOW WATER OR OTHER CONTAMINANTS

TO CONTACT LIVE PARTS, POSSIBLY RESULTING IN

SEVERE PERSONAL INJURY, DEATH, OR PROPERTY

DAMAGE.

Securely attach the flexible connectors supplied by

the switchgear manufacturer to the switchgear bus

bars. The number of flexible connectors supplied

is determined by the transformer current and not

by the current rating of the bus bar. Check the

length of flexible connectors and ensure that there

is approximately 0.375 inch (10 mm) of slack. This

will permit some movement of the bus bars to allow

for expansion and contraction and possible settling

of the transformer. Securely attach the ground bus

connection between the transformer and switchgear.

Before reinstalling the adapter housing, check for

adequate electrical clearances as indicated on the

outline drawing and check tightness of connections and

supports. Complete the installation by assembling the

housing. Install the adjustable plate and ensure proper

gasket sealing of the switchgear throat.

Pre-energization Tests and Checklist

The following tests and checks should be performed at

a minimum to ensure that the transformer is ready to

be energized. Do not energize the transformer without

performing these tests and checks.

1. Insulating Fluid Test. Draw a fluid sample and

test its dielectric strength. Dielectric strength

of the new fluid should be 26 kV or greater.

2. Pressure Test. Check the transformer tank for

leaks by pressurizing the tank with dry air or

dry nitrogen through the pressure test fitting

to a pressure of 3 to 4 PSIG. Let the tank

stand under pressure for one to two hours,

then examine the tank and fittings for leaks.

Leaks above the fluid level can be detected

by applying soap solution to all welds, joints,

pipe fittings, and cable connections. Upon

completion of this test, reduce the internal

pressure to 1 or 2 PSIG.

3. Insulation Megger Test. Perform a 1000-Volt

Megger test and a power factor test to ensure

that none of the windings are grounded.

4. Ratio Test. Perform a ratio test at each tap

position to ensure that transformer coil ratios

and tap changer connections are correct.

5. Continuity Test and Resistance Test. Perform a

continuity check on each winding.

6. Line Connections. In preparation for making

line connections, check to make sure that

all mating connector surfaces are clean and

smooth. Connections must be tightened

appropriately to prevent overheating and

possible subsequent failure of the connection.

Connections should be made with care to avoid

placing undue stress on the bushings.

7. Tap Changer Setting. Check the tap changer

setting to ensure it is set to the proper position

for the required voltage.