Smooth ICE/Flavored ICE Cover Installation

S A M S O N S P L I C I N G I N S T R U C T I O N S

Marking and knOTTing

1

step

2

step

Lay out rope to be covered and from the end to be covered, measure off distance to be covered and make

Mark 1 on the rope. From Mark 1, measure off a distance of 15 inches and make Mark 2 on the rope.

Lay out Ice cover below rope to be covered and allow 15% more cover length than rope to be covered from Mark

1 to the end of the rope. Then make Mark 1 on the cover using Mark 1 on the rope as a guide. Next make Mark 2

and Mark 3 on the cover by measuring off 6 inches for each mark.

Feed rope into cover and milk cover

over rope until Mark 1 of cover and

Mark 1 of rope are matched. Then

lock stitch the cover to the rope from

Mark 1 back for 3 complete passes.

3

step

Tape and cut the Ice cover at Mark 3. Then extract the internal feed line from the cover at Mark 1. Attach feed line

to rope end to be covered by passing the feed line through the rope braid and forming a loop knot. Be careful not

to pull the feed line into the cover on the other end.

Attach feed line from other end of cover

to a fixed point for assistance in burying

the rope into the cover.

4

step

5

step

Ice cover plus 15% extra length

Mark 1

Mark 2

Mark 3

Section of rope to be covered

Mark 1

Mark 2

15"

Attached feed line to rope with loop

knot. Tape for smooth transition

between feed line and rope

Extract feed line at

Mark 1 on cover

Mark 1

Tie off 1 end of feeder core

Lock stitch cover to rope

pusher

Insert fid at

Mark 1 on rope and exit at Mark 2

Cover, insert in fid.

6

step

Insert a splicing fid, fid should be sized to rope diameter, with the cover into the rope as

close to the lock-stitch as possible. Continue pushing the fid through the center of the

rope and extract the fid and cover at Mark 2 on the rope.