Window Installation Instructions - Typical Subframe Installation Section

Subhead/Subjamb Prepara on and Installa on 

 Typically EFCO will send subjambs long for field fit.  The sill 

end of the subjambs may have some type of notch cut by 
EFCO when required.   

 When the subjambs come pre‐notched at the sill end, all 

length adjustment should be done to the head end.   

 All notching will be done in the field by the installer on 

“Express Jobs”.   

 All anchorage clear holes, blocking, sealants, and perimeter 

fasteners are not by EFCO. 

 Measure for the sub jamb lengths.  See ver cal “X” and “Y” 

dimensions as indicated in the figure. 

 Subtract the “Y” dimension from the “X” dimension.  

Square cut the subjambs to this length from the head end 
of the subjamb. 

 Install the subjambs plumb, shimming as necessary. 

 The subhead will typically be square cut the width of the 

rough opening minus 1/2”. 

 Install the subhead using the subjambs as a guide.  

 Fasteners and shims are by the installer. 

 Cover all fastener heads with sealant to ensure water  ght 

seal.  Tool the sealant around the fastener heads so that 
the sealant makes contact with the face of the subframe. 

 Note: The sealing of the subhead and subjambs to the

condiƟon is criƟcal to the performance of the assembly and
will vary greatly based on the building condiƟon. The loca-
Ɵon of these seals will be shown on the shop drawings.

Shim; high impact 
shims may be required 
at some loca ons 

Subhead 

Subjamb 

Subjamb closure 

Sill condi on 

Head condi on 

Subsill 