Install Sleeves:
Dig footing holes and install the ground sleeves as shown in Figure 2.
Pour 6” concrete footing and allow fully curing, or use two concrete blocks or crushed
stone, to rest sleeve on. Wait 24 hours before inserting poles.

Figure 2

Install Pole Hardware:
Assemble 3/8” eyebolt hardware & 1/4" cleat hardware and pole cap onto the poles as
shown in Figure 3 & Figure 4. Route the hoisting rope through the pulley. Attach the
snap hook to the hoisting rope with a bowline knot. Temporarily attach the free end of the
hoisting rope to the snap hook.

Figure 3

Concrete, block or crushed stone.

Concrete

Note these are suggested dimensions for average
soil conditions, consult local building codes.

3/8"-16 x 5" LONG THREADED EYEBOLT

3/8" FLAT WASHER

4" ROUND RIBBED INSERT CAP

3/8"-16 HEX HD LOCKNUT

1 1/2'' SWIVEL PULLEY

5/16” x 3 1/8” SNAP HOOK

HOISTING ROPE x 45 FT

LONG (BOW LINE KNOT)

3/8" FLAT WASHER

TOP OF POLE

5/16” x 3 1/8” SNAP HOOK

TEMPORALLY TIE ROPE

~