Cdv series direct vent gas fireplace, Below grade installations, Vertical through-the-roof applications – Vermont Casting 36CDVTRN User Manual

Page 18

Advertising
background image

18

CDV Series Direct Vent Gas Fireplace

20010175

Below Grade Installations

When it is not possible to meet the required vent ter-
minal clearances of 12” (305 mm) above grade level
a snorkel vent kit #7TDVSNORK is required. It allows
installation depth of down to 7” (178 mm) below grade
level. The 7” is measured from the center of the hori-
zontal vent pipe as it penetrates through the wall.

If venting system is installed below
ground, we recommend a window well with
adequate and proper drainage.

Ensure sidewall venting clearances are observed.

The maximum horizontal run with 24”
vertical rise is 36” (914 mm) from the
back of the fireplace to the face of the
exterior wall. See vent graph (Page 12) for
extended horizontal run if the vertical rise
exceeds 24” (610 mm).

1. Establish vent hole through the wall. (Fig. 13)
2. Remove soil to a depth of approximately 16”

(406mm) below base of snorkel. Install window
well (not supplied). Refill hole with 12” (305 mm) of
coarse gravel leaving a clearance of approximately
4” (102 mm) below snorkel. (Fig. 30)

3. Install vent system. See Page 12, Steps 2 through 5.
4. Ensure a watertight seal is made around the vent

pipe coming through the wall.

5. Apply high temperature sealant caulking (supplied)

around the 4” and 7” snorkel collars.

6. Slide into the vent pipe and secure to the wall.
7. Level the soil to maintain a 4” (102 mm) clearance

below snorkel. (Fig. 30)

Do not back fill around snorkel. A
clearance of at least 4” (102 mm) must be
maintained between the snorkel and the
soil.

BG401

Snorkel

2/10/99 djt

Foundation Recess

Snorkel

Wall Screws

Recess Brackets

Watertight Seal

Around Pipe

Sheet Metal

Screws

BG401

Fig. 31 Snorkel installation, recessed foundation.

BG400

Below grade installation

2/10/99 djt

10/19/99 added standoffs

24" (610mm)

Minimum*

Firestop

7” Pipe

7TDVSNORK

(Snorkel)

4” (102mm)

Clearance

Min.

Window

Well

Gravel

Drain

Foundation Wall

BG400

Fig. 30 Below grade installation.

*A minimum of 24” (608mm)

vertical pipe must be installed

when using 7TDVSNORK Kit.

If the foundation is recessed, use recess brackets (not
supplied) for securing lower portion of the snorkel.
Fasten brackets to wall first, then secure to snorkel
with self drilling #8 x 1/2 sheet metal screws. It will be
necessary to extend vent pipes out as far as protruding
wall face. (Fig. 31)

Vertical Through-the-Roof Applications

CFM148

Maximum

10’

(3 m)

Minimum

8’ (2.4 m) /

Maximum

40’ (12 m) Vertical

Rise

CFM148

Pipe Straps Every

3’ (914 mm)

Fig. 32 Support straps for horizontal runs.

This Gas Fireplace has been approved for:
1. Vertical installations up to 40’ (12 m) in height. Up to

10’ (3 m) horizontal vent run can be installed within
the vent system using a maximum of three 90°
elbows.

2. Up to two 45° elbows may be used within the

horizontal run. For each 45° elbow used on the
horizontal level the maximum horizontal length must
be reduced by 18” (457 mm).

Advertising