Solution

a. On PTO drive units, check coupler between engine and pump.

Tighten if necessary.

b. With pump operating, clean hose leading to control box gauge by

using ball valve located on remote magnet mount.

c. Check gauge protector to see that it is filled with oil to within 1/8” of

top of threaded hole.

d. Swap agitation gauge and control box gauge to check for faulty

gauge.

e. Inspect electric solenoid valves to see that they are opening and

closing properly. Solenoid valves require 12 volts to open properly.

Valves may need cleaning, adjustment, repair kit or new coil. Low

voltage or a weak battery will result in valves not opening com-

pletely.

a. Check that manual pressure control valve is open.

b. Turn sprayer and engine off, hold the pressure adjust switch and

listen at the electric pressure control valve for whirring sound which

indicates that the motor is turning the valve.

c. With the engine running, visually inspect the nozzles to see if the

pressure is changing. If pressure is changing, clean hose leading

to control box gauge by using ball valve located on remote magnet

mount. If problem persists, swap agitation gauge and control box

gauge to check for faulty gauge.

d. If whirring sound is not heard, check electrical connections and fuse

in the control box.

e. If fuse is good, check with 12 volt tester to see fi pressure adjust

switch is receiving current from fused wire and sending signal to the

electric pressure control valve. Replace switch if faulty.

f. If current is good, check with 12 volt tester to see if pressure adjsut

switch is receiving current from fused wire and sending signal to the

electric pressure control valve. Replace valve if faulty.

a. Check electric pressure control valve operation as follows: With unit

spraying, hold the pressure adjust switch up. The pressure on the

control box gauge should increase to a maximum pressure, remain

high for about 10 seconds and then drop to minimum pressure.

Check wire connections, valve operation and voltage to switch and

valve. Replace valve if necessary.

b. Tank agitation may be restricted. Check that agitation valve is

open and agitator head has four jet streams shooting out.

c. Relieve excess pressure on electric pressure control valve. Open

electric pressure control valve to maximum pressure, then close the

manual control valve unit control gauge reads 15-20 psi above de-

sired nozzle pressure.

a. Check application guide for flow rate and catch nozzle flow to deter-

mine pressure drop.

b. Swap agitation gauge and control box gauge to check for faulty

gauge.

c. Check for clogged or pinched boom feed lines from solenoids.

d. Inspect electric solenoid valves to see that they are opening and

closing properly (Page 19). Solenoid valves require 12 volts to

open properly.

Valves may need cleaning, adjustment, repair kit or a new coil.

Low voltage or a weak battery will result in valves not opening com-

pletely.

Problem

4. Agitation gauge registers

pressure but control box

gauge reads zero or is very

sluggish after nozzles are

turned off.

5. Moving the pressure adjust

switch on the control box does

not change nozzle pressure

but both gauges show some

pressure.

6. Nozzle pressure cannot be

reduced below 20-30 psi.

7. During calibration control

box gauge reads about 30 psi.

Nozzles are spraying about 10

psi. When catching flow of

nozzles, there is a large pres-

sure drop.