10. Manual Fire and Fault Tests

After installation or cleaning, it is recommended that a Manual Fire and Fault test is performed:

Fire Test: Slowly half-cover the Receiver. The Controller will indicate Fire after the Fire Delay

Time.

Uncover the Receiver. The Controller will return to Normal state after approximately 5 seconds.

Fault Test: Completely cover the Receiver taking less than 2 seconds to do so. The Controller

will indicate Fault after the Fault Delay time.

Uncover the Receiver. The Controller will return to Normal state after approximately 5 seconds.

11. Remote Fire Test

The Remote Fire Test allows the user to perform a Fire Test from the System Controller.

The Remote Fire Test is acceptable for Fire Authority Acceptance and Routine Maintenance per

UL 268-5.

Receiver Fire LED Test

The Receiver will signal 'Fire',

the System Controller will stay

Normal.

Press

to exit without

performing the test.

Relay / Controller Wiring Test

The System Controller signals

'Fire' to the Fire Control Panel.

Press

or

to exit.