Meter Equalization Lug

Plastic Pipe

Plastic Pipe

#6 AWG Stranded

Copper Ground Wire

Ground Clamp

8’ Ground Rod

Earth

Exothermically weld when

corrosion is a concern

EQUALIZATION AND GROUNDING

Metal Pipe Installations.

To equalize the electrical potential

of the fluid, the iMAG meter, and the surrounding pipe, secure
the flange plates (factory-installed on the equalization wire)
to both pipe flanges at one of the bolt holes, as shown below.
Be sure the lockwasher fits between the pipe flange and the
flange plate. For the best electrical bonding, remove rust
and paint to expose clean, bare metal where the equlization
flange plate lockwasher contacts the pipe flange. Connection
must be inspected periodically for corrosion to maintain the
necessary low resistance connection.

Equalization Diagram

Equalization Lug

Meter

Flange

Pipe

Flange

Bolt

Run wire from equalization lug to both pipe flanges;

secure flange plates under bolt heads as shown.

Meter Flange

Pipe Flange

Flange Plate

Lockwasher

WARNING: ELECTRICAL SHOCK HAZARD

When

the meter is externally AC powered the piping

system must be grounded to meet national and

local electrical safety codes. Failure to do so can

result in electrical shock and/or burn.

Plastic Pipe Installations.

When the iMAG is installed in a

plastic piping system, it is not necessary to use the equaliza-
tion straps, but very important to ground the meter to avoid
electrical shock hazard and electrostatic interference with
meter function. If the rate display is unstable, grounding
rings may be necessary.

INSTALLATION

Positioning the Meter.

These meters can be installed

horizontally, vertically, and in any radial position. Using a

check valve on the upstream side of the meter, and/or an air

vent (vacuum relief valve) in the same, unobstructed run of

pipe as the meter, is required in any installation where the

meter may be exposed to suction when the system is not in

normal operation. Suction can cause damage to the liner.

Liner damage caused by suction, without the use of a check

valve and/or air vent, may void the warranty.

Straight Pipe Recommendations.

As with most flow meters,

the iMAG requires straight pipe before and after the meter for
best accuracy. However, the ability of electromagnetic meters
to average the flow across the entire pipe allows for shorter
straight pipe recommendations than most mechanical meters
(see page 7).

Full Pipe Recommendations.

All magmeters require a

method for determining that the pipe is empty, to prevent false
reading. This meter is designed to indicate ‘EMPTY PIPE’ if one
or more electrodes is exposed. For highest accuracy, install
the meter so that the pipe will be full when there is flow. If air
bubbles may be present in the pipe or sludge accumulation
is an issue, rotate the meter by one flange hole to position
the control housing at a 45˚ angle (see diagrams on page 8).

Fittings.

The iMAG flanges have standard ANSI 150 lb. drilling

pattern and mate with any other ANSI 150 lb. flange.

Calibration.

The iMAG is factory-calibrated and will not require

any form of field calibration.

Caution:

These flow sensors are not recommended

where installation fault may expose the flow sensor to

boiler pressure and temperature. Maximum

recommended operating temperature is 130˚ F.

INSTALLATION and GROUNDING

Chemical Injection.

When any magmeter, by any manufac-

turer, is used in a chemical injection application, the chemical
injection point must be placed downstream of the magme-
ter OR far enough upstream for complete mixing to occur
before the fluid reaches the meter

. When unmixed chemical

alternates with water passing through the meter, the rapid
changes in conductivity may cause sudden spikes and drops
in the meter’s reading, resulting in inaccurate measurement.
The magmeter will restabilize, however, with a steady flow of
fluid of uniform conductivity.

Metal

Pipe

Metal

Pipe

Caution:

In chemical injection applications, install

chemical injection point downstream of magmeter,

or far enough upstream to allow complete mixing

of fluids.

Partially Open