Preparing the AutoBlock

Follow the instructions for uncrating from the quality control sheet supplied with the unit or introduction
section of this manual. Follow the installation procedure step by step to insure proper function of the unit.


Note:

Residual water may be found in the internal plumbing of your AutoBlock. This includes the pump,

reagent injection lines and drain lines. This water is non-hazardous, and was used for system check
during quality control inspection.





Space & Weight Requirements

Lift the AutoBlock from the bottom only. The unit weights approximately 200-lbs. carefully place the unit
on a sturdy counter with the following minimum requirements:

• Counter must be able to support a minimum 300-lb load.

• Space requirements: 38”W x 32”L x 26”H these are the minimum requirements. Additional space will

be needed for reagents & a carboy placed under the unit.












Lift Compartment

Pumping
Compartment

electrical connections

Exhaust
Compartment

Exhaust vent

Graphite Block
Compartment

reagent ports

Injection Arm

JC1

JC2

JC3

Power module/ Voltage / Fuse


ABP164

on/off switch

Ventilation

The AutoBlock exhaust is located on the top right portion of the unit. Install a 4” diameter acid-resistant
duct and clamp to the exhaust outlet. Vent using state & federal guidelines. When connecting ductwork,
verify zero to negative pressure to prevent backflow. The length of the duct should not exceed 25’. Vent
the duct to the outside of the laboratory building or plumb into the existing ductwork.