Carrier AQUAZONE 50VQP084-300 User Manual

Page 11

Advertising
background image

11

• Boiler drains and other valves should be connected using

a “T” connector to allow acid flushing for the heat

exchanger.

• Do not overtighten connections.

• Route piping to avoid service access areas to unit.

• Use PVC SCH80 or copper piping material.
NOTE: PVC SCH40 should not be used due to system high

pressure and temperature extremes.
Water Supply and Quantity — Check water supply. Water

supply should be plentiful and of good quality. See Table 2 for

water quality guidelines.

In all applications, the quality of the water circulated

through the heat exchanger must fall within the ranges listed in

the Water Quality Guidelines table. Consult a local water treat-

ment firm, independent testing facility, or local water authority

for specific recommendations to maintain water quality within

the published limits.

Step 8 — Field Power Supply Wiring

All field-installed wiring, including the electrical ground,

MUST comply with the National Electrical Code (NEC) as

well as applicable local codes. In addition, all field wiring must

conform to the Class II temperature limitations described in the

NEC.

Refer to unit wiring diagrams Fig. 27-30 for a schematic of

the field connections which must be made by the installing (or

electrical) contractor. See Tables 3 and 4 for fuses sizes.

Consult the unit wiring diagram located on the inside of the

compressor access panel to ensure proper electrical hookup.

The installing (or electrical) contractor must make the field

connections when using field-supplied disconnect.

Operating voltage must be the same voltage and phase as

shown in electrical data shown in Tables 3 and 4.

Make all final electrical connections with a length of flexi-

ble conduit to minimize vibration and sound transmission to

the building.

POWER CONNECTION — Line voltage connection is

made by connecting the incoming line voltage wires to the

L side of the CC terminal. See Tables 3 and 4 for correct

wire and maximum overcurrent protection sizing.
SUPPLY VOLTAGE — Operating voltage to unit must be

within voltage range indicated on unit nameplate.

On 3-phase units, voltages under load between phases must

be balanced within 2%. Use the following formula to deter-

mine the percentage voltage imbalance:
% Voltage Imbalance

Example: Supply voltage is 420-3-50.

AB = 425 volts

BC = 422 volts

AC = 417 volts

Determine maximum deviation from average voltage:
(AB) 425 – 421 = 4 v

(BC) 422 – 421 = 1 v

(AC) 421 – 418 = 3 v
Maximum deviation is 4 v.
Determine percent voltage imbalance.

= 0.95%

This amount of phase imbalance is satisfactory as it is

below the maximum allowable 2%.

Operation on improper line voltage or excessive phase

imbalance constitutes abuse and may cause damage to electri-

cal components.
NOTE: If more than 2% voltage imbalance is present, contact

local electric utility.
420-VOLT OPERATION — All 380/420 volt units are factory

wired for 380 volts. The transformers may be switched to

420-volt operation (as illustrated on the wiring diagram) by

disconnecting the VIO lead at L1 and attaching the BRN lead

to L1. Close open end of VIO lead.

IMPORTANT: Failure to comply with the above required

water quality and quantity limitations and the closed-

system application design requirements may cause damage

to the tube-in-tube heat exchanger that is not the responsi-

bility of the manufacturer.

WARNING

To avoid possible injury or death due to electrical shock,

open the power supply disconnect switch and secure it in

an open position during installation.

CAUTION

Use only copper conductors for field-installed electrical

wiring. Unit terminals are not designed to accept other

types of conductors.

= 100 x

max voltage deviation from average voltage

average voltage

Average Voltage =

425 + 422 + 417

3

=

1264

3

= 421

% Voltage Imbalance = 100 x

4

421

Advertising