INITIAL START UP

Pre-Start Inspection

1. Remove the front, left, and right side service

panels.

2. Check that any styrofoam shipping blocks have

been removed.

3. Inspect the interior of the machine for loose

screws or wires. Check that no refrigerant lines

are rubbing each other. Check that the fan blade

turns freely (remote condenser).

4. Check that the refrigerant lines are properly

installed.

5. Check that the electrical power has been on for

at least 4 hours.

6. Check that the unit is installed correctly

according to the final check list on page 11.

Start Up

1. Go through the pre-start inspection.

2. Open the hand valve, observe that water enters

the water reservoir, fills the tube from the reservoir

to the evaporator, and then shuts off. Check for

leaks.

3. Open the King Valve.

4. Turn the master switch on.

The electrical start up sequence is automatic.

A. There should be a short (15 second) delay

before the gearmotor starts.

B. After the gearmotor starts, the liquid line valve

will open, the low pressure control will close and

the compressor will start.

5. The remote condenser fan turns, and the

condenser begins to discharge warm air.

6. The unit should soon be making ice, if desired

the low side pressure can be checked, it should be

30 PSIG + or - 4 PSIG. The discharge pressure will

depend upon air and water temperatures, but

should be between 180 PSIG and 300 PSIG.

7. THERE ARE NO ADJUSTMENTS TO MAKE,

so replace the panels.

8. Clean and/or sanitize the storage bin interior,

wipe off the exterior with a clean, damp cloth.

9 Give the owner/user the service manual, instruct

him/her in the operation of the unit, and make sure

they know who to call for service.

10. Fill out the manufacturers registration and mail

it to Scotsman.