C. Mounting the Boom Arm Assembly to the

Housing Boom Column (Figure #3)

1. Slide a Thrust Washer (720428) onto the shaft of the

Boom Column Assembly.

2. Apply some #2 lithium based grease to the shaft of the

Boom Column.

3. Install the Boom Arm Assembly (720285.17) onto the

shaft of the Boom Column Assembly.

4. Slide a second Thrust Washer (720428) onto the shaft

of the Boom Column Assembly.

5. Secure the Boom Arm Assembly and Washers to the

shaft with a Lock Nut (720580).

6. As needed, insert some #2 lithium based grease

through the grease fitting provided in the Boom Arm
Assembly.

7. Install Linch Pin (720437) as shown.

DISCHARGE CHUTE

ROTATE TO

DESIRED POSITION

FIGURE #4

KNOB

DISCHARGE

CLAMP RING

NUT

Figure #4

BOOM ARM ASSEMBLY

FIGURE #3

LINCH PIN

GREASE FITTING

BOOM COLUMN

LOCK NUT

THRUST WASHER

THRUST WASHER

Figure #3

D. Mounting the Discharge Chute to the

TruckLoader Housing (Figure #4)

1. Slide the Discharge Clamp Ring (720262.17) over the

Discharge Chute and down onto its flange.

2. Lift the Discharge Chute’s flange (720200) with the

Discharge Clamp Ring (720262.17) and place on top
of the Transition Discharge Tube’s flange (720461) as
shown.

3. Align the mounting holes of the Discharge Clamp Ring

(720262.17) with the bolts on the Transition Discharge
Tube’s flange (720462.10).

4. Secure the Discharge Clamp Ring (720262.17) to the

Transition Discharge Tube’s flange (720462.10) by
lightly fastening a Nut (64229-03) and Knob (38524) in
an alternating pattern as three of each are provided.

5. Position the Discharge Chute into the receiver box of

the transport vehicle and tighten down the Nuts and

Advertising