Warning, Danger, Before and after initial ergization – Howard HI-110 Network Transformer User Manual

Page 11

Advertising
background image

Document 2.4.128, Revision 2

August, 2012

11

Network Transformer Instruction Manual

BEFORE AND AFTER INITIAL ERGIZATION

Pre-Energization Inspection and Tests

After the transformer has been installed, but before

it is energized, the following tests and checks should

be performed at a minimum to ensure that the

transformer is ready to be energized. Do not energize

the transformer without performing these tests and

checks.

1. Continuity and Winding Resistance Test

Perform a continuity test to confirm

continuity of all windings. Perform a winding

resistance test and compare the measured

values with factory test data. An increase of

more than 10% may indicate a loose internal

connection.

2. Ratio Test

Using a transformer turns ratio (TTR) tester,

perform a ratio test to verify the proper

primary-to-secondary winding ratio. The

measured value should be within 0.5% of the

voltage ratio indicated on the transformer

nameplate. If the transformer is provided

with high-voltage taps, measure the ratio

at each tap position to verify that each of

the ratios is correct. Follow the instructions

and safety precautions provided by the TTR

equipment manufacturer. For additional

information about ratio testing, refer to IEEE

Standard C57.12.90.

3. Insulation Resistance Test

Perform a 1,000-Volt insulation test (Megger

test) to measure the resistance of the

insulation between windings and from each

winding to ground. Follow the instructions

and safety precautions provided by the test

equipment manufacturer. Prior to the test,

bushings must be thoroughly cleaned with

denatured alcohol to remove any moisture

or contaminants that could influence the

test results. Insulation resistance should

measure at least 1.0 GΩ.

An insulation resistance test must not

be performed on a wye-wye connected

transformer with an Ho-Xo bushing without

first disconnecting the internal connection

between the primary and secondary neutrals.

This connection can be found on a terminal

FAILURE TO FOLLOW THE INSTRUCTIONS

BELOW COULD RESULT IN DEATH OR SERIOUS

PERSONAL INJURY AND MAY ALSO RESULT IN

DAMAGE TO THE EQUIPMENT.
• Do not energize the transformer using single-

phase switches or fuses. Use only gang-

operated three-phase switches to energize a

three-phase transformer

• Do not energize the transformer if the

primary switch handle is in the “GROUND”

position

• Do not operate the transformer with any of

the primary phases open.

• Only qualified personnel with appropriate

equipment should measure transformer

voltages.

• Wear personal protective equipment to

prevent injury from potential arc-flash or

contact with dangerous voltages.

• Make sure the transformer is properly

grounded at all times.

• Insulated dead-end caps or plugs must be

installed on all unused dead-front high-

voltage bushings. Dust caps must not be

used in place of insulated dead-end caps or

plugs.

• CT leads, if supplied, must be connected

to a metering load or shorted together and

grounded to prevent dangerous voltages at

the CT terminals.

• Do not operate the tap switch while the

transformer is energized from either the

primary or secondary side.

WARNING

SECTION 4: INSPECTION AND TESTING

DANGER

FAILURE TO FOLLOW THE INSTRUCTIONS BELOW

WILL RESULT IN DEATH OR SERIOUS PERSONAL

INJURY AND MAY ALSO RESULT IN DAMAGE TO

THE EQUIPMENT.
Be aware of dangerous voltages and avoid

personal contact with live terminals

Advertising