CHAPTER 8 – SPARE PARTS

Page 116 of 156

AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913

OMM-0100_0B

PRI - 07/14/14

Ph.: 800-526-0288

GF-146

6.1.1 Checking for Gas Leaks

• Inspect all gas piping and verify to be leak free.

• Check for gas leaks: using soap solution, check for gas leaks from meter to appliance

including all pipes and fittings and heater connection. Use liquid soap solution for all gas
testing.

6.1.2 Flue and Air inlet Piping Inspection

• Check for obstructions, condensation, corrosion and physical damage, water stains, any

signs of rust, other corrosions or separation of the vent and air intake piping.

• Check outside terminations. Screens and louvers should be free of any debris and must

be cleaned as required.

6.1.3 System Piping, Pressure, and Expansion Tank Inspection

• Check water piping and accessories for leaks. All leaks should be corrected.

• Check that the system is filled with water and the reading on the pressure gauge remains

stable.

Eliminate all system and unit leaks. Continual fresh makeup water will reduce boiler life.
Minerals can build up in sections, reducing heat transfer, overheating heat exchanger, and
causing heat exchanger failure. Leaking water may also cause severe property damage.

6.1.4 Ignition and Flame Sensor Inspection

To inspect and maintain the ignition and flame sensor, perform the following:

Ignition and Flame Sensor Inspection

1. Remove the fan-burner assembly unit per Section 6.1.16.

2.

Remove any deposits accumulated on the ignition/flame sensor electrode using sand paper.

3. Check the positioning of the electrodes per Section 6.1.17.

4. Reinstall the fan-burner assembly back into the unit.

6.1.5 Wiring and Connections Inspection

Inspect all heater wiring, making sure wires are in good condition and securely attached.

6.1.6 Performance Verification Inspection

• Start the unit and perform a combustion calibration test as per Section 4.7.

Verify cold fill pressure is correct and that operating pressure does not go too high (if so,
check for problems with the expansion tank).

6.1.7 Flame Inspection

Inspect flame through the observation window on the burner.

If the flame is unsatisfactory at either high fire or low fire, clean the burner per Section
6.1.16.