CHAPTER 7

MAINTENANCE

Page 90 of 166 AERCO International Inc. • 100 Oritani Dr. • Blauvelt, NY 10913 • Ph: 800-526-0288 PR1:10/18/12

Benchmark 1.5LN Low NOx Boiler

Installation, Operation and Maintenance Manual

GF-120

OMM-0041 0E

7.9 PLACING THE BOILER BACK IN SERVICE AFTER A PROLONGED
SHUTDOWN

After a prolonged shutdown (one year or more), the following procedures must be followed:

1. Review installation requirements included in Chapter 2.

2. Inspect all piping and connections to the unit.

3. Inspect exhaust vent, air duct (if applicable).

4. Perform initial startup per Chapter 4.

5. Perform safety device testing and scheduled maintenance procedures per Chapters 6

and 7 of this manual.