LAARS Rheos RHCV - Install and Operating Manual User Manual
Page 39
Rheos Boiler and Water Heater
Page 39
6. Switch on the appliance power switch located on
the front of the unit.
7. The Rheos will enter the start sequence. The
blower and pump come on for pre-purge, then
the ignitor warm-up sequence starts and after all
safety devices are verified, the gas valve opens. If
ignition doesn’t occur, check that there is proper
gas supply. Wait 5 minutes and start the unit
again.
8. Open air orifice test port valves. Check air
orifice differential at full fire, and make note of
the differential.
9. Switch the Rheos off.
10. Close air orifice valves, remove the barbs and
replace the plugs. Make sure the connections are
gas tight.
11. Remove the two plugs from the + and – ports of
the gas orifice taps, thread hose barbs into the
1/8" NPT connections, and attach the manometer
pressure lines to the barbs. Be sure all
connections are gas tight.
12. Switch on the appliance power switch located on
the front of the unit.
13. The Rheos will enter the start sequence. The
blower and pump come on for pre-purge, then
the ignitor warm-up sequence starts and after all
safety devices are verified, the gas valve opens.
14. Open gas orifice test port valves. Check gas
orifice differential at full fire, and make note of
the differential.
15. Close gas orifice valves, remove the barbs and
replace the plugs. Make sure the connections are
gas tight.
16. If gas and air orifice differentials match what
is shown in Table 10, and do not differ from
eachother by more than 0.1" w.c., the unit is
properly set up. If not, consult, the factory.
17. After placing the appliance in operation, the
Burner Safety Shutoff Device must be tested.
To test:
(a) Close gas shutoff valve with burner
operating.
(b) The flame will go out and blower will
continue to run for the post purge cycle.
One additional attempt to light will follow
including pre-purge, ignitor on, valve/flame
on and post purge. Ignition will not occur
as the gas is off. The ignition control will
lockout, and will have to be reset before the
unit will operate.
(c) Open gas shutoff valve. Restart the
appliance. The ignition sequence will
start again and the burner will start. The
appliance will return to its previous mode
of operation.
Valve
Valve
Shown
Open
Closed
Shown
Figure 34. Gas/Air Test Panel.
Figure 35. Test Panel Valves.
- LCH504T - Installation Manual
- Combi Heat TTW - Installation Manual
- Custom ASME Storage Tanks - Installation Manual
- EBP 110 MBTU/h - Installation, Operation and Maintenance Instructions
- IGE-199R - Installation Manual
- IGE-199R-10(N,X) - Service Manual
- IGI-180R - Installation Manual
- IGI-180R-10(N,X) - Service Manual
- EverHot (interior) Venting Components - Installation Manual
- Heat Exchanger - Installation Manual
- Gateway RER - Manual
- INDIRECT-FIRED - Installation, Operation and Maintenance Instructions
- M4-LHS - Installation Manual
- MagnaTherm MGH - Installation, Operation and Maintenance Instructions
- Mascot LX MLXH 50 MBH - Install and Operating Manual
- MC4EXT - Install and Operating Manual
- Mighty Stack MS-080 (Sizes 199, 300, 399) - Install and Operating Manual
- Mighty Therm HH-PH (Sizes 175-400) - Installation, Operation and Maintenance Instructions
- Mighty Therm VW-PW (Sizes 175-400) - Installation, Operation and Maintenance Instructions
- Mighty Therm AP (Sizes 2000-5000) - Installation, Operation and Maintenance Instructions
- Mighty Therm HH (Sizes 2000-5000) - Installation, Operation and Maintenance Instructions
- Mighty Therm VW (Sizes 2000-5000) - Installation, Operation and Maintenance Instructions
- Mighty Therm AP (Sizes 500-1825) - Installation, Operation and Maintenance Instructions
- Mighty Therm HH (Sizes 500-1825) - Installation, Operation and Maintenance Instructions
- Mighty Therm VW (Sizes 500-1825) - Installation, Operation and Maintenance Instructions
- Mighty Therm2 MT2H (Sizes 500–2000 MBTU/h) - Install and Operating Manual
- Mighty Therm2 MT2H (Sizes 200, 300, 400) - Install and Operating Manual
- Mighty Venter MV1 (Sizes 175-400) - Install and Operating Manual
- Mighty Venter MV2 (Sizes 500-1825) - Install and Operating Manual
- Mighty Therm2 MT2P (Sizes 500–2000 MBTU/h) - Install and Operating Manual
- Mini-Therm JVH (Sizes 50-225) - Install and Operating Manual
- Multi Flue CF-38-3 - Install and Operating Manual
- NeoTherm LC NTH1000 - Install and Operating Manual
- NeoTherm LC NTH (Sizes 1000-1700 MBTU/h) - Installation Manual
- NeoTherm NTH (Sizes 285–850 MBTU/h) - Installation Manual
- NeoTherm NTH (Sizes 080–285 MBTU/h) - Service Manual
- NeoTherm NTH (Sizes 080–850 MBTU/h) - Start Up Guide
- NeoTherm NTH (Sizes 080–850 MBTU/h) - Install and Operating Manual
- NeoTherm NTH (Sizes 399-850 MBTU/h) - Service Manual
- Pennant PNCP - Install and Operating Manual
- Pennant PNCH (Sizes 500-2000) - Install and Operating Manual
- Pennant PNCH - Install and Operating Manual
- Rheos Side-Wall Ducted Combustion Air Terminal - Service Manual
- Rheos Side-Wall Vent Termination - Service Manual
- Rheos Vent Terminal - Service Manual
- Rheos+ RHHH - Install and Operating Manual
- S8 - Installation Manual
- BT-20 - Installation Manual
- U.H.E. - Installation Manual
- U.H.E. - Service Manual
- X-BAC BACnet Interface Module - Install and Operating Manual
- XSIG - Install and Operating Manual
- EBP Series - Users Manual
- Mascot LX MLXH 50 MBH - Users Manual
- Mighty Therm2 MT2H (Sizes 200, 300, 400) - Users Manual
- Mighty Therm2 MT2H (Sizes 500–2000) - Users Manual
- Mini-Therm JVH (Sizes 50-225) - Users Manual
- NeoTherm LC NTH1000 - Users Manual
- NeoTherm NTH (Sizes 080–850 MBTU/h) - Users Manual
- Pennant PNCH (Sizes 200, 300, 400) - Users Manual
- HWG-M2-250 - Service Manual
- CB-M2-150 - Installation, Operation and Maintenance Instructions
- CB-M2-150 - Users Manual
- 9600 HWG - Installation, Operation and Maintenance Instructions
- DuraFlow - Installation, Operation and Maintenance Instructions
- EBP Series - Installation, Operation and Maintenance Instructions
- EBP Series - Installation, Operation and Maintenance Instructions
- HW-M2 Series - Installation, Operation and Maintenance Instructions
- Horizon - Installation, Operation and Maintenance Instructions
- LLS-1 - Instruction Manual
- M4 - Installation Manual
- M4-CNC - Installation Manual
- Mascot ll LMC - Users Manual
- Mascot ll LMC - Start Up Guide
- Mascot ll LMC - Install and Operating Manual
- MAX 75 (DV) - Installation, Operation and Maintenance Instructions
- Mighty Max HH (Sizes 320M - 1000M) - Installation, Operation and Maintenance Instructions
- Mighty Max HH (Sizes 320M - 400M) - Installation, Operation and Maintenance Instructions
- Mighty Max VW (Sizes 320M - 400M) - Installation, Operation and Maintenance Instructions
- Mighty Therm LO-NOx HH (Sizes 250/400) - Install and Operating Manual
- Mighty Therm LO-NOx PH (Sizes 500-1825) - Install and Operating Manual
- Mighty Therm LO-NOx PH (Sizes 500-1825) - Install and Operating Manual
- Mighty Therm LO-NOx PW (Sizes 250/400) - Installation, Operation and Maintenance Instructions
- Mighty-Stack TL00-199 - Installation, Operation and Maintenance Instructions
- Mighty-Stack TL80-199 - Installation, Operation and Maintenance Instructions
- Mini-Combo II MCT - Install and Operating Manual
- Mini-Combo id MCH - Install and Operating Manual
- Mini-Therm II JVS (Sizes 50-225) - Install and Operating Manual
- Mini-Therm JVi - Install and Operating Manual
- NeoTherm NTH600 - Install and Operating Manual
- NeoTherm NTH1000 - Install and Operating Manual
- Newport - Installation, Operation and Maintenance Instructions
- Pennant PNCH (Sizes 200, 300, 400) - Install and Operating Manual
- SC6 - Install and Operating Manual
- SUMMIT SMB-200 - Install and Operating Manual
- SUMMIT SMB-200 - Users Manual