DNF Controls UABS-I Installation_Manual User Manual

Page 6

Advertising
background image

5

5 of 5

Flex Control Network

®

UABS-I Installation Manual

2. DC20 INSTALLATION

CAUTION
Do NOT apply AC voltage to power supply, then connect power supply to
DC20 Device Controller. Component damage may occur.

1) Connect Cat 5 cable to DC20 connector labeled “E-NET #1”. Connect

other end of Cat 5 cable to customer supplied Ethernet hub.

2) Plug one end of a standard 9-conductor, RS422 serial cable into the

Serial Port #1 connector on the rear of the DC20.

3) Plug the other end of the 9-conductor, RS422 serial cable into the

remote control connector on the VTR, DDR, or Video Server. Repeat

steps 2 and 3 for each serial port to be used for machine control.

4) Connect facility video reference to REF video connector on rear of

DC20. This is required for accurate play timing.

5) Connect facility time-of-day LTC to LTC Input Connector on rear of

DC20. This is required for accurate gang synchronization.

6) Connect power supply DB9 female connector to DC20 connector

labeled “POWER“.

7) Connect female side of power cable to supplied power supply.
8) Connect male side of power cable to AC voltage, 100 – 240.
9) Push DC20 power switch, located on front panel, to ON position. The

“O” on the power switch is the OFF position.

10) Front panel LEDs will flash during power up. When power up and

system initialization completes, the front panel LEDs will turn off and

the front panel display will show Model Number and Software Version.
Allow 45 seconds for power up and system initialization to complete.

No connection is required to the DIAGNOSTIC or VGA connectors on the rear
of the DC20.

CAUTION
Do NOT apply AC voltage to power supply, then hot plug power supply to
DC20 Device Controller. Component damage may occur.

Advertising