Input wiring (tb1), Output wiring (tb3) – Liebert NfinityTM User Manual

Page 16

Advertising
background image

Installation

12

Input Wiring (TB1)

To connect the input wiring, follow these steps:
1. Locate the input wiring access, remove the knockout and

pull the three input wires through it, allowing some slack

for installation.

2. Secure the conduit to the rear panel of the UPS.
3. Input Power cables connect to screw terminals on the

Input Terminal Block located to the right of the Bypass

Voltage Terminal. Connect the wires to the block

connections as shown below. Using a torque wrench, turn

the screws clockwise until tightened to the proper torque

value (28 in-lb). Insert the ground wire through the

grounding lug and tighten it to the proper torque value

(120 in-lb).

Grounding Conductor Installation
An insulated grounding conductor must be identical or larger

in size, insulation material, and thickness as the grounded

and ungrounded branch circuit supply conductors. This cable

must be green with or without one or more yellow stripes and

is to be installed as part of the branch circuit that supplies

the unit or system.
The grounding conductor is to be grounded to earth at the

service equipment or, if supplied by a separately derived sys-

tem, at the supply transformer or generator set.

Output Wiring (TB3)

Refer to the chart below and the diagram at right

when configuring the output wiring.

Voltage

105

210

Between terminals

1 & 3,

2 & 3

1 & 2

Use only the connections listed above. Other connections will
produce nonstandard voltages.

NOTE
The Nfinity UPS contains an isolation

transformer that generates a neutral

conductor for the connected equipment.

The UPS is a separately derived source

and contains a neutral to ground bonding

jumper. A grounding electrode conductor

(GEC) must be installed in accordance

with national and local wiring codes and

regulations.

TB1

L1

L2

2

1

Note the Neutral / Earth
jumper on the terminal
above

105V

210V

105V