SET-UP AND POURING INSTRUCTIONS

JOB SITE SET-UP FOR APĆ

PLICATIONS USING SIDE

DRIVE UNIT (24" AND

LARGER).

1. The road bed for the paver must be

graded up to approximately 10'

wide (depending on hopper size).

Begin about 2' outside the curb

edge to about 8' towards the center

of the roadway. The grading

should be approximately 8' beĆ

yond the curb end point. Grade

must be flat within approximately

1/2". Compacting the grade will

help provide traction for the paver.

ROAD CENTER LINE

CURB OUTSIDE EDGE

2'
8'

PAVER TRAVEL DIRECTION

2. Standard stakes, arms and string

line are suitable for the paver. The

string line should be set up approxĆ

imately 18" to 24" left of the curb

line (to the outside of the roadway)

and 18" to 24" above the grade.

Pull the string as tight as possible.

This will ensure the most accurate

operation of the paver's on-board

computer sensor system.

18"-24"

18"-24"

CURB & GUTTER POUR

NOTE: Recommended stringline setup for 24" hopper or above is 20" x 20"

MACHINE SET-UP:

1. Start the paver engine. (See Starting the Engine", page 16.)
2. Flip Main Power and Hydraulic Power ON.
3. Check all hydraulic functions.