VERTICAL SEAM

32

p

eak

o

ver

d

eckIng

Double Bead Tape Sealant

1

/

8

x

3

/

16

" Pop Rivet (see below)

Vertical Seam Clip

Peak

Vertical Seam Panel

Vertical Seam Z-Closure
#10-12 x 1" PHW (4 per panel)

Tube Sealant

Double Bead Tape Sealant

Cleat
#10-12 x 1" PHW (1'-0" o.c.)

Moisture Barrier (by others)

1. Once panels have been installed, field cut the Vertical Seam Z-Closure (see page 47) to fit between the panel ribs.

2. Place a row of Double Bead Tape Sealant across panel and over each panel rib approximately 2" from panel end. Before

proceeding make sure Z-Closure placement will accommodate Peak cover.

3. Install field cut Z-Closure (as shown on page 47).

4. Fasten Z-Closure through panel with #10-12 x 1" Pancake Head Woodscrews. (4 per panel)

5. Apply a row of Double Bead Tape Sealant across top leg of Z-Closure filling any gaps or openings around panel ribs.

6. Position and install Cleat to the wall with the appropriate fastener, 1'-0" o.c. Make sure cleat allows for proper Peak attachment.

7. Install Peak flashing by sliding the open hem onto the Cleat and then attaching to the Z-Closure with

1

/

8

" x

2

/

16

" Pop Rivets, at

the spacing shown above.

8. If two or more flashings are required, lap the flashing over the previously installed flashing by a minimum of 2” placing a bead

of Tube Sealant between the flashings and securing with pop rivets 2

1

/

2

" o.c.

Pop Rivet

Flashing

Z-Closure

Tape Sealant

INSTALLATION NOTES

CAUTION

Additional screws

may be required for

high snow loading

and steep slopes.

1:12 Slope

Minimum

over Solid

Substrate