6 Commissioning

Requirements

☐ The AC cable is correctly connected.
☐ The DC cable is correctly connected.
☐ The enclosure lid is securely closed.
☐ The miniature circuit-breaker is correctly rated.

6.1 Switching On the Sunny Boy

1. Remove all covers from the PV array.
2. Switch on the AC miniature circuit-breaker.
3. Turn the DC Disconnect to position "1",

☑ The Sunny Boy performs an AFCI self-test.

High voltages in the PV plant during solar irradiation
Risk of death or serious injuries due to incorrect commissioning.

• Only commission the Sunny Boy in the following order.

AFCI Self-test

Only the following types of Sunny Boy perform an AFCI self-test:

• SB 6000TLUS-12
• SB 7000TLUS-12
• SB 8000TLUS-12
• SB 9000TLUS-12
• SB 10000TLUS-12
• SB 11000TLUS-12