SMA SB 6000TL‑US Installation User Manual

Page 44

Advertising
background image

6  Commissioning

SMA America, LLC

44

SB6-11TL-US-IA-en-13

Installation Manual

☑ If the AFCI self-test is successful: The Sunny Boy switches into the

"Waiting" mode and the green LED flashes. The "Waiting" mode ends
when there is sufficient solar irradiation. The green LED is permanently lit
and the Sunny Boy feeds into the power distribution grid.

or

☑ If the AFCI self-test fails: The yellow LED flashes. The Sunny Boy repeats

the AFCI self-test until it is successful. Observe Section 6.2 "The Sunny Boy
Does Not Resume Operation", page 45.

If the Sunny Boy does not operate as expected, refer to the user manual.

If the feed-in to the power distribution grid was interrupted by a detected AC failure and then
resumed, the inverter waits 5 minutes before feeding in again.
For this, the input voltage must be greater than the start voltage of the Sunny Boy. For the
corresponding values, see section 11 "Technical Data", page 70.
If the inverter is not able to feed into the power distribution grid three times in a row, it waits
10 minutes before the next attempt.

Advertising