Commissioning steps, Commissioning, Switch−on sequence commissioning steps – Lenze EVS9332xP User Manual

Page 164: 2 commissioning steps

Advertising
background image

Commissioning

Switch−on sequence
Commissioning steps

6

6.3
6.3.2

l

6.3−2

EDSVS9332P EN 5.0−07/2013

6.3.2

Commissioning steps

Switch−on sequence

Comment

1.

Ensure that controller inhibit is active after mains
connection.

misc008

59

28

X5

}

Terminal X5/28 = LOW

2.

Ensure that no external error is pending.

Terminal X5/E4 = HIGH

3.

Switch on controller.

A

The control card is operated via an external voltage
supply:
Switch on the external DC 24 V supply voltage.

ON

misc002

B

The control card is operated via an internal voltage
supply:
Switch on the mains. The controller provides the DC
24 V supply.

4.

After approx. 2 s the controller has initialised.

5.

Switch on the PC and start GDC.

GDC starts in the online mode if the PC
and the controller are connected to
each other.
Information on the connection
establishment can be found in the
"Global Drive Control (GDC) − Getting
started" manual.

6.

Do you want to use an existing configuration and
positioning?

A

Yes.
Load the desired parameter set to the controller.

^ 6.12−3
Then continue with step 11.

B

No.
Configure controller and generate positioning.

Continue with step 7.

7.

Enter the machine parameters in GDC.

A

Select the basic configuration.
Lenze setting: C0005 = 1000 (basic configuration
˜speed control˜).

^ 6.5−1

B

Adapt the controller to the mains.

^ 6.5−1

C

Enter motor data.

^ 6.5−3

D

Set temperature monitoring of the motor.

Motor with PTC or thermal contact:

^ 6.5−12
Motor with KTY:

^ 6.5−13

E

Select feedback system.

^ 6.6−1

8.

If required, carry out a current controller
adjustment.

^ 6.7−1

9.

If required, carry out a rotor position adjustment.

^ 6.8−1

10.

Configure the function of the control terminals to
adapt them to your application.

If an internal voltage supply is used,
assign "FIXED1" to X5/x and
"FIXED100%" to X6/x.

^ 6.9−1

11.

Check the travel range limit switches with the
manual control.

^ 6.10−1

12.

Enter the travel profile parameters.

^ 6.11−1

13.

Save the settings with mains failure protection in
one of the 4 parameter sets (C0003).
With C0003 = 1 the settings are saved in parameter
set 1.

After connecting the DC 24 V supply or
after mains connection, parameter set
1 is activated automatically.
(See chapter "Parameterisation")

14.

Carry out a homing.

^ 6.13−1

15.

Switch on the mains if previously only the external
DC 24 V supply voltage was switched on.