2 - applying power and resetting terminal, Chapter objectives, Wiring and safety guidelines – Rockwell Automation 2711 Standard PanelView Operator Terminal User Manual User Manual
Page 59: Chapter 2, Applying power and resetting terminal, Chapter objectives wiring and safety guidelines, Chapter

59
Publication 2711-UM014G-EN-P - September 2008
59
Chapter
2
Applying Power and Resetting Terminal
Chapter Objectives
This chapter provides information on:
•
wiring and safety guidelines.
•
connecting AC or DC power.
•
resetting the terminal.
•
power-up sequence.
Wiring and Safety
Guidelines
Use publication NFPA 70E, Electrical Safety Requirements for
Employee Workplaces when wiring the PanelView terminals. In
addition to the NFPA general guidelines:
•
connect the terminal to its own branch circuit.
•
the input power should be protected by a fuse or circuit breaker
rated at no more than 15 Amps.
•
route incoming power to the PanelView terminal by a separate
path from the communication cable.
•
where power and communication lines must cross, they should
cross at right angles. Communication lines can be installed in the
same conduit as low level DC I/O lines (less than 10V).
IMPORTANT
Do not run signal wiring and power wiring in the same
conduit.