Metrohm NIRS XDS Process Analyzer – DirectLight/NonContact User Manual

Page 37

Advertising
background image

▪▪▪▪▪▪▪

35

6.

These photos show a mounting with 3/8”

mounting studs, welded to a heavy
backing plate.

The mounting may also be a sturdy frame,
or other method suitable to support the full
weight of the instrument.

Use extreme caution with the fiber optic
cables when mounting the instrument. If
possible, the cables should be coiled up
and secured to the unit to avoid damage.
Radius of coiled fibers should never be less
than 6” (153mm). Diameter should be at
least 12” (305mm).

DO NOT EVER use the fiber optic cable
connection as a lifting point or “grab
handle.”

7.

Install a large washer, locking washer and

nut onto each of the two (2) upper
mounting studs.

Tighten nuts to the torque recommended
by the fastener supplier.

8.

The bottom right mounting foot is shown.

Be sure both lower mountings are securely
tightened.

9.

Verify that all four (4) mounting brackets are securely fastened to the mounting studs, and

that the hardware is tight.