Functional tests, Equipment required, Power-on check – AMETEK XFR 2800 Watt Series User Manual

Page 37: Equipment required –9 power-on check –9

Advertising
background image

Functional Tests

TM-F2OP-C1XN-01

2-9

Functional Tests

These functional test procedures include power-on and front panel
function checks as well as voltage and current mode operation checks.
Refer to front and rear panel diagrams in “Front Panel Controls” on
page 1–3

and

“Rear Panel Connectors and Switch” on page 1–5.

Equipment Required

Digital voltmeter (DVM) rated better than 0.5% accuracy.

DC shunt 1 mV/A (±0.25%) with connecting wire. The recommended
current ratings for the DC shunt and the wire must be at least 10%
more than the output current of the power supply.

Power-on Check

1. Ensure that the AC power switch is in the OFF position.

2. Ensure that the output sense lines are connected in the default

configuration. (The local sense lines are connected between
terminals 1 and 2 and between terminals 4 and 5 on the J10 sense
connector as shown on the rear panel diagram in Figure 1-2 on
page 1–5.
)

3. Turn the voltage and current controls fully counter-clockwise.

4. Connect the unit to an AC outlet.

5. Turn the front panel AC power switch to ON.

After a short, power-on delay, the front panel digital meters light up and
the green voltage mode LED turns on. Both voltmeter and ammeter
displays read zero.

Advertising