Deploying KIRK Wireless Server 600v3

14117800, Ed.2.6

3.2.2.1 Synchronization Chain With One Sync Master (Primary Sync Ways)

Figure 1

Synchronization Chain

• The synchronization chain must always overlap with the KWS600v3 to sync

on.

No. 100 is the Sync Master.
• Other radio units are connected to the Sync Master through the

synchronization chain.

• If one of the radio units in the synchronization chain is not working, then the

Figure 2

Synchronization Chain Layout without Alternative Sync Ways

No. 100 is the Sync Master (can be numbered 1-255).

Note:

It is recommended to place the Sync Master in the middle of the building.

Green line

: Shows the primary sync ways.

Brown line

: Only handover overlap is needed.

Note:

It is recommended to make a site planner. Every KWS600v3 must be

numbered with Radio ID, Primary sync Radio ID, and Alternative sync Radio

ID.