5.8 | proper wiring

IMPORTANT! DAMAGE CAN OCCUR!

Check polarity of all wiring! If continuity is reversed with regard to the power CABLING (16

gauge, 2 conductor) at any point, some or all of the OPs will be irreversibly damaged.

MAKE SURE THAT between power zones a ground wire is ONLY installed connecting the

separate power zones/supplies.

MAKE SURE THAT YOU have connected to each Power Supply the correct wire to the low
voltage side AND that each wire is correctly connected to the appropriate and proper + and

-

.

VISUALLY INSPECT AND DO NOT LEAVE TO CHANCE!

You may turn on each power supply in sequence.

Visually inspect to insure that the i.Lon® server and MPI (if one is purchased for the project)

are properly wired and installed.

ONCE YOU HAVE VISUALLY INSPECTED EACH ITEM AND ESTABLISHED

CONFIDENCE THAT THERE IS CORRECT CONTINUITY THROUGHOUT THE POWER

WIRING, YOU MAY PROCEED TO THE NEXT STEP!

MAKE SURE ALL OPS ARE WIRED CORRECTLY

AND FOLLOW CONTINUITY THROUGHOUT

THE ENTIRE SYSTEM (+ AND –).