FINAL WIRING CHECKLIST BEFORE POWERING UP SYSTEM

Have you checked all home runs?

Have you checked all wiring between floors (risers)?

Are you sure all grounds are properly tied between i.Net OPs?

Have you made sure all Data and Speaker wires are tested and installed?

Check polarity of all wiring throughout, especially power cables. If continuity is

reversed at any point, some or all of the i.Net OPs will be irreversibly damaged.

NEVER WORK WITH POWER WIRE, OR CONNECT POWER WIRES TO

I.NET OPs, WHILE POWER IS ON.

2

4

5

1

3

TIP

TIP! Check data wires

by going to the Sound

Manager Configurator and

refreshing i.Net OPs after

each i.Net OP

is connected. This will

help to eliminate large

trouble shooting issues

at the end of the job.

WARNING

NEVER WIRE or CONNECT

POWER TO AN i.Net OP WHILE

POWER IS ON!!! i.Net

OP will

lose its number identity.

Always connect wire to i.Net

OP while power supply is

not plugged in.