Installation and Configuration
Steps

Installation and configuration has several phases. In some cases, a
separate person is responsible for each phase. It is important to
coordinate the activities among the persons involved.
The customer or vendor installs the APs per the Configuration Guide
for the AP being used. This is normally done before the SpectraLink
8000 Telephony Gateway installation, but should be done before step
3 below.
The first two steps are usually done by the customer up to the point of
installing and connecting the SpectraLink 8000 Telephony Gateway(s)
to the telephone demarc blocks and LAN access device. At that point,
a qualified Polycom installer assists the customer in completing the
remaining steps.

1. Site Preparation: Done by the customer or a wire

technician/contractor.

2. SpectraLink 8000 Telephony Gateway Installation: Done by

the customer or Polycom.
If five or more SpectraLink 8000 Telephony Gateways are to be
installed, a SpectraLink 8000 SVP Server is required and would
also be installed in this step.

3. SpectraLink 8000 Telephony Gateway Configuration: Done by

the customer or Polycom.
Conditional:
SpectraLink 8000 SVP Server Configuration: If a SpectraLink
8000 SVP Server has been installed, its configuration would also
be done in this step per SpectraLink 8000 SVP Server Administration
Guide for SRP.

4. SpectraLink Wireless Telephone Configuration: Done by the

customer or Polycom specialist per SpectraLink [model] Wireless
Telephone Administration Guide
.

5. System Certification: Done after installation to confirm the

system is working properly per SpectraLink [model] Wireless
Telephone Administration Guide
.