Chapter Five--Control Setup

2. Name the Zone. (Figure 5-7)
3. Choose Grouped or Sequenced operation. (Figure 5-7)

Figure 5-7

Name the Zone

Choose grouped or
sequenced from the
dropdown

5. Select a breaker to add to the zone by clicking on the

breaker you want to add. Only motorized breakers
(indicated in green) may be added to zones. (Figure 5-8)
Scroll down to add breakers from additional panels.

6. Select the position of the breaker in the zone. This set

the order in which they turn on and off . (Figure 5-9)

7. For sequenced operation, select a delay time from the

dropdown. Breakers in grouped zones toggle in 25ms
intervals. (Figure 5-9) Delay time is the amount of time
after a breaker changes state, before the new breaker
in sequence changes state.