Installing an mx480 scb, Figure 87: removing an scb – Juniper Networks MX480 User Manual

Page 199

Advertising
background image

Figure 87: Removing an SCB

Installing an MX480 SCB

To install an SCB (see

Figure 88 on page 176

):

1.

Attach an electrostatic discharge (ESD) grounding strap to your bare wrist, and connect
the strap to one of the ESD points on the chassis.

2.

Carefully align the sides of the SCB with the guides inside the chassis.

3.

Slide the SCB into the chassis until you feel resistance, carefully ensuring that it is
correctly aligned.

4.

Grasp both ejector handles, and rotate them simultaneously clockwise until the SCB
is fully seated.

5.

Place the ejector handles in the proper position, horizontally and toward the center
of the board.

6.

Check the LEDs on the SCB faceplate to verify that it is functioning normally.

The green

OK/FAIL

LED should light steadily a few minutes after the SCB is installed.

If the

OK/FAIL

LED is red, remove and install the SCB again. If the

OK/FAIL

LED still

lights steadily, the SCB is not functioning properly. Contact your customer support
representative.

7.

Check the status of the SCB using the

show chassis environment cb

command:

user@host>

show chassis environment cb

CB 0 status:
State Online Master
Temperature 25 degrees C / 77 degrees F
Power 1
1.2 V 1198 mV
1.5 V 1508 mV
1.8 V 1830 mV
2.5 V 5059 mV

175

Copyright © 2013, Juniper Networks, Inc.

Chapter 14: Replacing MX480 Hardware Components