Figure 33: contents of the shipping crate – Juniper Networks MX480 User Manual

Page 86

Advertising
background image

To unpack the router (see

Figure 33 on page 62

):

1.

Move the shipping crate to a staging area as close to the installation site as possible,
where you have enough room to remove the components from the chassis. While the
chassis is bolted to the pallet, you can use a forklift or pallet jack to move it.

2.

Position the shipping crate with the arrows pointing up.

3.

Open all the latches on the shipping crate.

4.

Remove the front door of the shipping crate cover and set it aside.

5.

Slide the remainder of the shipping crate cover off the pallet.

6.

Remove the foam covering the top of the router.

7.

Remove the accessory box and the Quick Start installation instructions.

8.

Verify the parts received against the lists.

9.

Remove the vapor corrosion inhibitor (VCI) packs attached to the pallet, being careful
not to break the VCI packs open.

10.

To remove the brackets holding the chassis on the pallet, use a 1/2-in. socket wrench
and a number 2 Phillips screwdriver to remove the bolts and screws from the brackets.

11.

Store the brackets and bolts inside the accessory box.

12.

Save the shipping crate cover, pallet, and packing materials in case you need to move
or ship the router at a later time.

Figure 33: Contents of the Shipping Crate

Related

Documentation

Verifying the MX480 Router Parts Received on page 63

Installing the MX480 Router Mounting Hardware for a Rack or Cabinet on page 65

Installing the MX480 Router Using a Mechanical Lift on page 74

Tools Required to Install the MX480 Router with a Mechanical Lift

Tools Required to Install the MX480 Router Without a Mechanical Lift on page 83

Copyright © 2013, Juniper Networks, Inc.

62

MX480 3D Universal Edge Router Hardware Guide