First ivar will be inserted ahead of label count, thus getting number 4, which makes
RETURN fall back to 3.
Then jump count gets inserted ahead of Var6 and thus gets number 5. This effects that
label count (before then having 5), output ivar3 and RETURN each get numbered down
by 1.
At last the AND box will be re-inserted ahead of jump count and thus will get number
4. This again effects a reducing of the numbers each for label count (before then
having 4), output ivar3 and RETURN by 1. So the following new order of execution will
arise:

Abb. 82

Sequence afterwards


Also a new element always will be inserted in the sequential processing list ahead of
its topological successor.

Set Execution Order
This command (category CFC) by default is part of submenu "Execution Order" in the
CFC menu. It serves to redefine the element number of the currently selected element
in order to change the position of this element within the execution order.
The command opens the dialog 'Set Execution Order'. The current element number is
displayed in field Current Execution Order and you can enter the desired new one in
New Execution Order. The possible values are displayed in brackets.

Abb. 83

Dialog 'Set Execution Order'